Illustrative sample. The plant, the weeks and the footage are synthetic.
Approved fixes get an update every week. Paused, Declined and Done do not. In this sample the weekly reports are already written, so changing a status here does not change them.
We watch how long a job switch takes on each press, from the press cameras and the ERP job log. Target: about 30 minutes faster per job switch.
Extra profit a year once this is running, after what it costs to run. Profit, not revenue.
Minutes cut off each mold change, time the press spends making parts instead of sitting stopped. It pays once you fill it with sold work or smaller batches.
Capex
$22,000
Payback
5 months
Difficulty
2 / 5
Time to implement
~12 weeks
This plant molds plastic parts on about 26 injection presses and runs a high mix, so the presses are constantly stopped to swap one heavy steel mold for the next.
SMED, single-minute exchange of die, cuts the dead time in a mold change by doing everything possible while the press still runs, then making the actual swap fast.
The math
30 min × 2,200 changeovers / 60
1,100 hrs × $55/hr × 90% filled
Deep dive
SMED is a discipline, not a purchase. Without audits, crews drift back to the comfortable old sequence and the changeover times climb back to where they started.
Changeover times on the monitoring dashboard creep upward week over week.
Standard-work audits tied to the uptime data, with the drifting shift retrained.
Most of the $55K.
Quick clamps speed the bolt-up, but if the next mold and its tools are still not staged, the press waits anyway and the hardware never earns back.
Presses still wait on molds and tools even after the clamps go in.
Fix the staging carts and kitting first; buy hardware only where the clamp-up is the proven bottleneck.
The entire hardware ROI.
A rushed startup on a fresh change can ship out-of-spec first parts before the process settles.
Startup scrap spikes right after a changeover.
First-article checks and a documented startup recipe on every change.
A customer return, plus a possible re-validation.
The change gets fast but nothing is done with the recovered time, so the presses just idle longer between the same jobs.
Changeover times fall while output and work-in-process stay flat.
Decide up front whether the freed time buys new work, smaller batches, or on-time delivery, and hold someone to it.
The capacity value, though the batch-shrink cash release still lands.
Every task in a mold change is one of two things. Internal tasks need the press stopped: unclamp the old mold, lift it out, set the new one, bolt it up, hook the water and hydraulics. External tasks can be done while the press is still making parts: find the next mold, pre-heat it, gather the tools, stage the crane. Most shops do far too many external tasks after the press stops, wasting paid press time. SMED is mostly the discipline of moving that prep to before the press stops, so the actual dead time shrinks to the few things that truly require a stopped machine.
The 63-minute median is not the real problem; the shift-to-shift spread is. When the same job takes one crew 40 minutes and another 100, the scheduler cannot plan, so the whole floor pads its estimates and the plan drifts. A reliable, repeatable 30-minute change is worth more than a one-off 15-minute change that only the best setter can hit. Standardized sequences and staged carts attack the spread directly, which is why on-time delivery often improves more than the raw minutes would suggest.
Quick clamps, magnetic platens, and multi-couplers are real and they work: vendors document changes dropping from an hour to fifteen minutes on a single press. But they fix exactly one thing, the manual clamp-and-hookup step. If the press is waiting because the next mold was never staged, no clamp will help. Prove with the video that the bolt-up is the remaining bottleneck before spending $10K to $30K a press on hardware, or the money sits idle bolted to a press that is still waiting on a cart.
Freed changeover hours convert three ways, and this card is firmer than the OEE card because two of them do not need new sales. First, fill the hours with sold work (the capacity gate, same as everywhere). Second, run smaller batches, which releases work-in-process cash straight off the balance sheet. Third, hit delivery dates you were missing, which protects and wins customers. Because the batch-shrink and delivery paths pay without waiting on the sales pipeline, most of the recovered hours here are readily usable, which is why the value is discounted only lightly.
The records we did not have for this read and would ask for on day one. Each one replaces an estimate on this card with your own number.
To confirm the roughly 63-minute median and, more important, the shift-to-shift spread on this floor, which sets both the minutes-saved figure and how much predictability there is to gain.
This is the multiplier the whole saving scales off. A shop running thousands of changes a year gets far more from thirty saved minutes than one running a few hundred.
To see whether staging or clamping is the real bottleneck, which decides whether the money goes to carts and kitting or to quick-change hardware.
To size the startup-waste reduction from a standardized change and to set the first-article check that keeps faster changeovers from causing escapes.