To improve
A press sat idle while its first parts waited at the lab
Aug 25
After a job switch, the press had to stop until the lab approved its first parts. The lab was busy with a customer return, and first parts likely just wait their turn.
Hours of press time lost while the press was ready to run, the longest stop that day.
We looked at the camera recording and the ERP quality records.
Put first parts ahead of all other lab work, even customer returns.
Who owns it: Quality manager (Priya Shah)
Benchmark: Press OEE