Press 18 and pad printing. Aug 31. ERP order records.
The bracket order after its first day, stage by stage
What it shows: The ERP shows when each stage of the bracket order started and how far each got by the end of the night shift.
Why it proves the point: Printing started the same day as molding and ended the day only about 1,000 brackets behind it.
From the plant's ERPERP order records
| Stage | Started | Brackets done | Still to do |
|---|---|---|---|
| Molding on press 18 | Aug 31 | 15,000 | 25,000 |
| Pad printing on both shifts | Aug 31 | 14,000 | 26,000 |
| Packing and shipping | Not started | None | 40,000 |