Press 18 to the shipping dock. Aug 31 to Sep 3. ERP order records.
The bracket order from molding to shipping, stage by stage
What it shows: The ERP shows when each stage of the bracket order started and finished.
Why it proves the point: Pad printing started the same day as molding and ran on both shifts, so the order never sat waiting.
From the plant's ERPERP order records
| Stage | Started | Finished | Days before the promised date |
|---|---|---|---|
| Molding on press 18 | Aug 31 | Sep 2 | 3 days |
| Pad printing on both shifts | Aug 31 | Sep 3 | 2 days |
| Packing | Sep 3 | Sep 3 | 2 days |
| Shipping | Sep 3 | Sep 3 | 2 days |