Press 5. Sep 8 to Sep 11. ERP job log.
Each wait for a mold so far, and the press time it cost
What it shows: The ERP job log shows how long press 5 waited for each mold, how long each swap took and the whole stop.
Why it proves the point: Each swap took under an hour, so most of the 8 hours press 5 was stopped went to waiting for molds.
From the plant's ERPERP job log
| Date | Waiting for the mold | Swapping the mold | Press stopped for |
|---|---|---|---|
| Sep 8 | 1 hour 30 minutes | 55 minutes | 2 hours 25 minutes |
| Sep 9 | 2 hours 10 minutes | 55 minutes | 3 hours 5 minutes |
| Sep 11 | 1 hour 40 minutes | 50 minutes | 2 hours 30 minutes |
| Sep 8 to Sep 11 | 5 hours 20 minutes | 2 hours 40 minutes | 8 hours |