Pythia Industries

Sample Plant

Jul 22

Two presses sat idle waiting for a late plastic delivery

Urgent

The plastic was likely reordered with too little stock left to cover a delay in delivery.

What happenedTwo presses ran out of plastic and sat idle, waiting on a delivery that had not come. Their plastic was reordered with only about a day of stock left.
Why it mattersBoth presses lost most of the time they were scheduled to run, and still had no plastic.
Next stepReorder this plastic while several days of stock are still left.
OwnerMaterials lead
Evidence

Both presses stopped with their plastic supply boxes empty

The supply boxes that feed the two presses are empty, and both presses sit stopped behind them. Both presses are stopped with nothing left to feed them, so the lost time is waiting for plastic, not a fault.

Supply boxes for presses 23 and 24, Jul 22, 5:15 pm, Camera 9

The plastic reorder that left too little stock to spare

The ERP shows when the plastic was reordered and promised, when it ran out, and that it had not arrived. The order left only about 8 hours to spare, too little to cover a delivery that did not come on time.

Presses 23 and 24, Jul 21 to Jul 22, ERP purchasing records

From the plant's ERP
StepWhenPlastic left
Reorder placedJul 21, 2:15 pmAbout 1 day of use
Delivery promisedJul 22, 8:00 amAbout 8 hours of use
Plastic ran outJul 22, 4:30 pmNone
Still no deliveryEnd of the Jul 22 night shiftNone

The new knob job ran its first full day with little scrap

Going well

Nearly every knob came out good on all three shifts, keeping the low scrap the job started with.

What happenedA press ran its first full day on a new knob job, and nearly every knob came out good. Its scrap has stayed near 1 percent since the job started on Jul 21.
Why it mattersCompared with the plant's usual scrap, the extra good knobs keep adding up.
How to keep it upKeep the press on the settings the lab approved so its scrap stays this low.
OwnerQuality manager
Evidence

How few knobs the new job scrapped on both days

The ERP shows how many knobs the press made and how many were scrap each day on its new job. Both days stayed near 1 percent, even the first, when a new job usually scraps the most.

Press 14, Jul 21 to Jul 22, ERP scrap record

From the plant's ERP
DateKnobs moldedKnobs scrappedShare scrapped
Jul 2115,8001901.2 percent
Jul 2219,4001901.0 percent
Both days35,2003801.1 percent

Illustrative sample. The plant, the walk and the footage are synthetic.