Illustrative sample. The plant, the weeks and the footage are synthetic.

Pythia Industries
Sample Plant
Back to the Sep 8 report

Going well

A second welding machine started running on the night shift

Sep 8

  1. Parts had piled up waiting to be welded, so the second welding machine ran on the night shift for the first time. By morning the queue was down by about a third.

  2. Orders that need welding now get to shipping sooner, with less work piled up.

  3. Keep the second welding machine running at night while more than a day of work is waiting.

    Who owns it: Secondary operations lead (Nadia Karim)

Benchmark: On-time delivery