Going well
The welding queue kept shrinking after a second night shift
Sep 9
The second welding machine ran a second night in a row, and the pile of parts waiting to be welded kept shrinking. About a day of work is left, down from 3 days.
Orders that need welding now reach shipping sooner still, with less waiting at welding.
We looked at the camera recording and the ERP order records.
Keep the second welding machine running at night while more than a day of work is waiting.
Who owns it: Secondary operations lead (Nadia Karim)
Benchmark: On-time delivery