Aug 20 to Aug 26. ERP purchasing records.
The grinder order and the moved delivery date
What it shows: The ERP shows when the grinders were ordered, the date they were due and when that date moved.
Why it proves the point: The vendor moved the date on the day the grinders were due, leaving presses 9 and 10 without them another week.
From the plant's ERPERP purchasing records
| Date | What changed on the order | Delivery date |
|---|---|---|
| Aug 20 | Two grinders ordered, one each for presses 9 and 10 | Aug 26 |
| Aug 24 | Delivery date confirmed by the vendor | Aug 26 |
| Aug 26 | Delivery date moved by the vendor | Moved back 6 days |