Illustrative sample. The plant, the weeks and the footage are synthetic.

Pythia Industries
Sample Plant
Back to Cut changeover time with SMED

Presses 7 and 12. ERP job log.

Job switches with the tool cart and without it

What it shows: The ERP shows how long each job switch took, and the cameras show only the two on press 7 used a cart.

Why it proves the point: Press 7 averaged 46 minutes with its cart, while press 12 averaged 70 minutes without one.

From the plant's ERPERP job log
DatePressOld job endedNext job's first good partPress stopped for
Aug 25Press 128:20 am9:29 am1 hour 9 minutes
Aug 26Press 123:40 pm4:51 pm1 hour 11 minutes
Aug 27Press 710:15 am11:03 am48 minutes
Aug 28Press 77:30 pm8:14 pm44 minutes