Illustrative sample. The plant, the weeks and the footage are synthetic.

Pythia Industries
Sample Plant
Back to Cut changeover time with SMED

Press 12. ERP job log.

Job switch times with one setup person and with two

What it shows: The ERP shows how long each job switch on press 12 took and how many setup people were clocked on.

Why it proves the point: The one job switch with two setup people took 48 minutes, and the three with one took over an hour each.

From the plant's ERPERP job log
DateOld job endedNext job's first good partPress stopped forSetup people clocked on
Sep 19:10 am9:58 am48 minutesTwo
Sep 21:20 pm2:27 pm1 hour 7 minutesOne
Sep 39:40 pm10:49 pm1 hour 9 minutesOne
Sep 410:05 am11:17 am1 hour 12 minutesOne