Press 12. ERP job log.
Job switch times with one setup person and with two
What it shows: The ERP shows how long each job switch on press 12 took and how many setup people were clocked on.
Why it proves the point: The one job switch with two setup people took 48 minutes, and the three with one took over an hour each.
From the plant's ERPERP job log
| Date | Old job ended | Next job's first good part | Press stopped for | Setup people clocked on |
|---|---|---|---|---|
| Sep 1 | 9:10 am | 9:58 am | 48 minutes | Two |
| Sep 2 | 1:20 pm | 2:27 pm | 1 hour 7 minutes | One |
| Sep 3 | 9:40 pm | 10:49 pm | 1 hour 9 minutes | One |
| Sep 4 | 10:05 am | 11:17 am | 1 hour 12 minutes | One |