Implementation plan
1. Time the compressors at a meal break
One short reading shows whether the lines leak and whether pressure is spare.
| Action |
|
| Owner | Maintenance lead |
| Purchases | None: twenty minutes of staff time |
| Decision | Is a compressor loaded for over about two of the twenty minutes, or is its pressure well above the highest press setting? |
| Fallback | If neither, the work ends here and nothing has been bought. |
2. Walk the lines and fix the largest leaks
Each leak is found, tagged and fixed, the largest first, and the walk is repeated.
| Action |
|
| Owner | One named maintenance person |
| Purchases | An ultrasonic leak detector, about $1,500, and about sixteen hours of staff time for the first walk. Then hose, couplings and thread tape, about $160 per year |
| Decision | After the repairs, is a compressor loaded for fewer minutes than at the first reading? |
| Fallback | If a large leak cannot be reached while the plant runs, tag it and fix it at the next planned stop. |
3. Bring the setting down two psi at a time
The setting comes down only as far as every press still runs as before.
| Action |
|
| Owner | Maintenance lead, with the shift supervisor |
| Purchases | None: about four hours of staff time |
| Decision | Did every press run a full shift as before at the lower setting? |
| Fallback | If any press starves for air, raise the setting by two psi again and leave it there. |