Read together, the walk and the job log show presses waiting for things that could be ready before they stop.

On the walk

Press open, waiting for its mold

14:20 to 15:50

A press stood stopped and open while its next mold came from the rack. It made no parts meanwhile.

Checked by us on a still of the film

Three trips for hoses and tools

14:30 to 15:45

One person left the stopped press three times for hoses and tools. Nothing was set out beforehand.

Counted by us on stills of the film

Molds on racks in the mold shop

22:40

Molds stood on racks in the mold shop, none set out for its next job. The next mold starts here.

Checked by us on a still of the film

Mold fetched after the stop

23:05 to 23:14

Mold shop staff said the next mold is fetched when the press goes down. So each change waits.

Said by plant staff on the walk

Plant records

Mold changes in the job log

The job log shows 2,200 mold changes in a year. Half of them took longer than 63 minutes.

The ERP job log, twelve months

Changes on the busiest presses

Eight presses made about half of all mold changes. A fix fitted there reaches the most changes.

The ERP job log, twelve months

Illustrative sample. The plant, the walk and the footage are synthetic.