Pythia Industries

Sample Plant

Verification

Test
  • From the ERP job log, list last month's jobs by press.
  • Beside each job on a large press, note the smallest press its mold ran in during the last twelve months.
  • Mark each job where that press is at least two sizes smaller, counting each step on the plant's list of press sizes as one size.
  • Add up the hours of the marked jobs, and note whether a smaller press was idle at the time.
CostAbout $80: about two hours of the scheduler at a desk, at $40 per hour. Nothing is bought.
DurationAbout two hours at a desk
Confirmed ifThe marked jobs for which a smaller press stood idle add up to about 25 hours or more in the month.
Ruled out ifFew jobs are marked, or each marked job had its reason: the smaller press was booked, or the mold needs the wider opening or the bigger shot of a large press.

Illustrative sample. The plant, the walk and the footage are synthetic.