Implementation plan
1. Time the hand work at one press
One hour with a stopwatch shows whether one person can keep up with two presses.
| Action |
|
| Owner | Shift supervisor |
| Purchases | None: one hour of a supervisor, about $45 |
| Decision | Are the hands busy for less than about a third of each cycle? |
| Fallback | If they are busy for more than half, look at the gate work on that mold, the second way on the menu. |
2. Fit one pair of presses and run it for a week
One pair shows the real pace before anything more is bought.
| Action |
|
| Owner | Maintenance lead, with the shift supervisor |
| Purchases | Two chutes, two short belts and two counters, about $10,000 with fitting |
| Decision | Does one person keep up for a full week, with no more rejected parts than before? |
| Fallback | If the person falls behind on one job, keep the pair for the other job and try a different neighbor. |
3. Move the freed hours out of overtime
The saving is cash only when the freed person covers work that overtime covers today.
| Action |
|
| Owner | Production manager |
| Purchases | About $5,000 for each further press |
| Decision | Have overtime hours per week fallen by about the hours freed at the first pair? |
| Fallback | If overtime does not fall, hold the next purchase until the freed hours have a named use. |