Change cart and checklist

A cart brings the next mold, its hoses and its tools to the press before it stops, loaded from that mold's checklist.

Next jobMoldHosesToolsThe mold's own checklist1A cart holds the nextmold, hoses and tools
CostAbout $10,200
PaybackAbout 6 months
LimitationIt saves nothing on a change where the next job is not known before the press stops.

What changes

While the old job still runs, a cart brings the next mold to the press.

The same cart carries that mold's cooling water hoses, fittings and tools, picked from its checklist.

A mold too heavy for a cart waits on its pallet beside the press.

When the press stops, the swap starts at once and nothing is left to fetch.

What it costs and could save

  • Six carts with hoses and tools, and a checklist for every mold, cost about $10,200.
  • That could save about $20,300 per year, a payback of about 6 months.

Why it works

Mechanism
  • A press earns only while it makes parts.
  • Fetching a mold, hoses and tools does not need the press stopped.
  • It can be done while the old job still runs.
  • Each minute of fetching moved ahead of the stop is a minute the press runs.
  • The swap itself is not rushed, and the first parts are checked as they are today.
Math
  • We count 15 minutes off each of 2,200 mold changes per year, which is 550 press hours.
  • A freed press hour is counted at $55 when an order fills it, and we count 70 percent of them as filled.
  • That is about $21,200 per year.
  • Hoses, fittings and tools replaced on the carts take off about $900, which leaves about $20,300.
  • Six carts and the checklists cost about $10,200 once, a payback of about 6 months.
  • Each minute off a change is worth about $1,400 per year.
Industry evidence
  • The standard method for shortening a change moves every task that does not need a stopped machine to before the stop.
  • Published cases of injection molders that shortened their mold changes report cuts of 30 to 60 percent.
  • Our 15 minutes is about a quarter of the median change here.
  • Makers of clamps that need no bolts report a change of about a quarter of an hour on one press.
  • The minutes for a ready cart alone are our estimate until one change is timed.
Limitations
  • A freed press hour is money only when an order fills it.
  • We count 70 percent as filled, because about one order in seven shipped late last year, so orders do wait for presses.
  • If no order waits, the press only stands idle at another time and nothing is saved.
  • We saw one change, on one press, and did not time it.
  • The cart saves nothing on a change where the next job is not known before the press stops.
  • The minutes come back if a shift stops loading the cart ahead.
  • The job log's change times show it each week.

Illustrative sample. The plant, the walk and the footage are synthetic.