Implementation plan
1. Time one mold change in four parts
The timing shows how much of a change is waiting.
| Action |
|
| Owner | Shift supervisor |
| Purchases | None |
| Decision | Does the press wait more than about 8 minutes for the mold, hoses or tools? |
| Fallback | If the mold, hoses and tools are already at the press when it stops, there is nothing here to fix. |
2. Write a checklist for each mold
What each mold needs at a change is written down once.
| Action |
|
| Owner | Process technician on shift, with the mold shop |
| Purchases | None: about ten minutes for each mold, about $1,200 of a technician's time in all |
| Decision | Does a cart loaded from the list hold everything the change needs? |
| Fallback | If something is still missing, it is added to the list at that change. |
3. Load a cart before the press stops
The fetching moves from after the stop to before it.
| Action |
|
| Owner | Shift supervisor, with the mold shop |
| Purchases | Six carts with hoses and tools, about $9,000 |
| Decision | Is the next timed change shorter by about the minutes the first timing found in waiting? |
| Fallback | If carts are still loaded after the stop, one person loads them at the start of each shift. |
4. Read the change times each week
The job log shows whether the minutes stay off.
| Action |
|
| Owner | Plant manager |
| Purchases | None |
| Decision | Is the median mold change down to about 48 minutes? |
| Fallback | If it is not, time one change again in four parts to see where the minutes went. |