1. List scrap by mold and weigh three bins

The list names the molds, and the bins show whether the scrap is still being made.

Action
  • List last month's scrap by mold from the ERP, and by shift where it is recorded.
  • At the start of a shift, empty the scrap bins at the three molds highest on the list that are running, and at one other press.
  • At the end of the shift, weigh the rejected parts in each bin on the floor scale.
  • Note whether the fault sits in the same place on every part.
OwnerA process technician
PurchasesNone
DecisionDo the same few molds lead the list and fill their bins, with faults that change from part to part?
FallbackIf the fault sits in the same place on every part, that mold goes to the mold shop first.

2. Study the worst molds at the press

Short trials find the settings at which each mold makes good parts.

Action
  • Take one mold at a time, in its usual press, with its usual resin.
  • Change one setting at a time: fill speed, holding pressure, holding time, cooling time.
  • Weigh and check the parts of each trial, and note where they start to go bad.
  • Choose the settings in the middle of the band where parts stay good.
  • Where a customer has approved a part's settings, ask for sign-off before the new ones are used.
OwnerA process technician
PurchasesNone: about 72 hours of a technician and about 1,200 lb of trial parts, about $5,800 in all
DecisionDoes the mold make good parts across a band of settings, not only at one point?
FallbackIf no band is found, the mold or the resin is the cause, and the study of that mold stops.

3. Keep one signed sheet at each press

Every shift starts from the same settings, and a change carries a name.

Action
  • Write the chosen settings on one sheet and fix it at the press.
  • Every shift starts the job from the sheet.
  • A change is written on the sheet with a name, the time and the reason.
  • The technician reads the changes every week, and updates the sheet where a change holds.
  • Weigh the rejected parts of these molds every week for a month.
OwnerA process technician, with each shift's supervisor
PurchasesNone
DecisionDoes the weighed scrap on these molds fall, and stay down for a month?
FallbackIf the scrap returns on one shift, that shift starts its next run with the technician at the press.

Illustrative sample. The plant, the walk and the footage are synthetic.