Length of a stop
  • How long the last ten unplanned mold stops lasted, from the stop to the next good part.
  • We count 1.2 hours per stop, and the press hours in the figure rise and fall with it.
  • Who can answer: Shift supervisors.
Orders waiting for presses
  • Whether orders wait for the presses these eight molds run in.
  • A freed press hour is money only when an order fills it.
  • Who can answer: Whoever plans the jobs.